Primavera Tip: Run a Quick Pertmaster Risk Analysis

Conducting a detailed and thorough schedule or cost risk analysis can be a data intensive and time consuming effort. Proper conduct of the assessment process requires input from multiple responsible project team members. Though this process is necessary to provide a credible analysis there is one way to get a quick initial thumbnail sketch for any given project plan.

From the Pertmaster menu, select Risk, Duration Quick Risk, then specify whether you want to include “All tasks in the plan”, “All filtered tasks, or “Selected tasks only”; then specify a Distribution function and standard percentages for the Minimum, Likely and Maximum durations. Click OK and you’re all set to run the risk analysis. Repeat the same steps for resource costs.