Primavera Tip: Exporting Projects

Problem:  The customer, vendor or contractor has an older version of Primavera or another project management tool, and needs to view a schedule.

Solution: Export the project.

  • Open the desired project to be exported

  • Go to File>Export

March2009_Screenshot1
 
  • Choose the format including desired program and version. For Primavera PM/MM and Primavera Contractor, there are now several options for versions. 

 March2009_Screenshot2
 
  • For Microsoft Project, select the file type

     

 March2009_Screenshot3

  • Export type should be Project

  • Click Next (These fields will show you the file to be exported)

  • Click Next

 March2009_Screenshot4
  • Do not try to save the file to your C drive or any other local drive on your computer. Try saving to a network drive (in this example, the file is saved to the M: drive)

 March2009_Screenshot5
  • Click Finish