IMS
When results matter...

Primavera Tip: Automatically Calculate Percent Complete

Often managers are uncomfortable with the “guesstimate” given for percent complete. The Primavera steps feature becomes very useful when they are weighted to drive the percent complete in a way that is less subjective and more quantifiable. Generally, steps are a way to track deliverables or any sub-activity without adding activities and complexity to your schedule. Any group of steps that is often repeated (a typical document workflow for example) can be made into a step template for use on all such activities, too.

To have each step automatically drive physical percent complete for the activity:

1.    Open the columns within the step tab by right-clicking on the last column and selecting “Customize Column Headings”. Then select the Step Weight and Step Weight Percent columns and move them into the view by clicking the right arrow button on the middle frame. Click OK. The new columns appear on the steps tab.

2.     Now, define each step by importance or weight it carries toward overall completion of the activity. The cumulative physical percent complete is automatically calculated if the setting on the calculations tab at the project level is checked to “Activities with steps drive percent complete.” You may want to ensure the Physical Percent Complete column is viewable in the activity table or that this activity is set in the general tab to the Physical Percent Complete Activity Type. If you do not weigh them, then each step carries equal weight, so if you have ten steps then each one counts 10 % of the total physical percent complete.

Two examples: IT and Construction

Test 2000 Code Testing Activity

 Weight

Percent Complete After Step is Completed

 Step One: Unit Test One

 5

 5

 Step Two: Unit Test Two

 5

 10

 Step Three: Unit Test Three

 5

 15

 Step Four: Unit Test Four

 5

 20

 Step Five:  Integration Testing of One and Two

 10

 30

 Step Six:  Integration Testing, Add Three

 10

 40

 Step Seven:  Integration Testing, Add Four

 10

 50

 Step Eight:  System Test

 15

 65

 Step Nine:  Functionality Test

 25

 90

 Step Ten:  Move to Production

 10

 100

 

CON2000 Pre-Bid Cycle Activity for Carpentry Vendor Selection

Weight

 Percent Complete After Step is Completed

 Step One:  Bid Statement of Work (SOW)Drafted

 5

5

 Step Two:  Vendor Selection Criteria Agreed Upon

 5

10

 Step Three:  SOW Reviewed

 5

 15

 Step Four: SOW Approved

 5

 20

 Step Five:  Solicitation of Bids

 5

 25

 Step Six:  Bid Close, Vendor Selected

 30

 55

 Step Seven:  Vendor Notified

 5

 60

 Step Eight: Contract Drafted

 15

 75

 Step Nine:  Contract Revisions

 20

 95

 Step Ten:  Contract Approved

 5

100